33/11 kV KPHB
Point Name Status Voltage Amp MW MVAR MVA PF Update
33kV MIYAPUR KPHB_CB OPEN 0.09 0.00 0.00 0.00 0.00 0.00 Ok
33kV ERRAGADDA_CB CLOSE 33.74 168.59 9.62 -1.77 9.78 0.99 Ok
33kV MIYAPUR_IJM_CB OPEN 0.00 0.00 0.00 0.00 0.00 0.00 Ok
33kV HV_1_CB CLOSE 0.00 29.29 0.00 0.00 0.00 0.00 Ok
33kV HV_2_CB CLOSE 0.00 79.83 0.00 0.00 0.00 0.00 Ok
33kV HV_3_CB CLOSE 0.09 62.22 -0.01 -0.00 0.01 -0.96 Ok
11kV LV_1_CB CLOSE 11.03 84.76 0.00 0.00 0.00 0.86 Ok
11kV LV_2_CB CLOSE 11.32 238.04 0.00 0.00 0.00 0.76 Ok
11kV LV_3_CB CLOSE 11.23 184.55 0.00 0.00 0.00 0.80 Ok
11kV TRAVEW_CB CLOSE 10.99 26.16 0.47 -0.13 0.49 0.97 Ok
11kV HMT CLN_CB CLOSE 10.98 23.41 0.46 -0.05 0.47 0.99 Ok
11kV JALAVAYU VIHAR_CB CLOSE 10.98 37.18 0.72 0.15 0.73 0.98 Ok
11kV DHARMA REDDY_CB CLOSE 11.29 18.92 0.41 0.01 0.41 1.00 Ok
11kV HYDER NGR_CB CLOSE 11.30 61.55 1.12 -0.31 1.16 0.97 Ok
11kV 6TH PHASE_CB CLOSE 11.29 75.21 1.38 -0.51 1.47 0.94 Ok
11kV BHAGYA NGR_KPHB_CB CLOSE 11.21 26.25 0.50 -0.10 0.51 0.98 Ok
11kV JNTU_CB CLOSE 11.20 83.61 1.62 -0.33 1.65 0.98 Ok
11kV KPHB_CB CLOSE 11.21 62.38 1.17 -0.24 1.20 0.98 Ok

Report generated by HTML Interface on 05/11/24 08:57:40